07/15/2026
The Ramshorn Retaining Wall Project has officially started. Caulder Construction was on-site all last week hauling in fill to complete the access road to the area behind G Building, removing about 25 trees and installing silt fencing.
We have a Project KickOff call today with our Engineering Company overseeing the project, Verdantas Engineering (formerly Horizon Engineering), Caulder Construction and their Engineers and the Ramshorn B.O.D.’s.
Project is expected to take 4 to 6 weeks and will entail spreading 1,700 Cubic Yards of fill and installing many pre-engineered concrete blocks in the area to add additional support to secure the wall behind G Building and the expanded parking area.
Additionally, as a part of this project, we will finish replacing the last culvert as a part of the Culvert Replacement Project we addressed two years ago. This last culvert is the longest, deepest and most disruptive of all the culverts we replaced, as it runs under the road on the east end of H Building and continues under the road again, through the expanded parking area between F & G Buildings.
Please be aware that there will be a significant amount of construction activity on-going with a significant number of truck loads of fill and pre-engineered cast blocks being delivered to the site. Please try to stay clear of the area of possible and expect lots of noise and activity over the coming weeks.