Miigwetch Sound Studio Join me on this journey of turning my idea into a creative/comfortable working space for ALL artists. Opening fallish 2026, Please spread the word. Thank you!

We are converting a 3 bay garage into a world class hybrid audio/video recording studio.

Miigwetch Sound Sunday Update! Bulkhead in the control room,live room framed in, conduit is all run for the console and ...
07/26/2026

Miigwetch Sound Sunday Update! Bulkhead in the control room,live room framed in, conduit is all run for the console and outboard gear., HVAC is a work in progress! Thanks again for following along. Have a great week.🙋🏼‍♂️😄

07/26/2026

Miigwetch Sound Sunday update! SABIAN Gretsch Drums

Miigwetch Sound Sunday update! All the bulkheads in the live room and control room are framed, all the conduit has been ...
07/26/2026

Miigwetch Sound Sunday update! All the bulkheads in the live room and control room are framed, all the conduit has been ran, and the HVAC is a work in progress!

07/04/2026

Miigwetch Sound Friday night update!

Hello Everyone, we have finished all the layers of drywall, live room is taped/sanded, lounge is taped, control room sti...
07/04/2026

Hello Everyone, we have finished all the layers of drywall, live room is taped/sanded, lounge is taped, control room still needs to be screwed off and taped, HVAC half installed.. Bulkheads coming up next. I can see the finish line!!😁🙏

Friday night update, all the drywall finally done in the live room three layers 15,000 screws, and now the control room ...
06/20/2026

Friday night update, all the drywall finally done in the live room three layers 15,000 screws, and now the control room fully insulated starting boarding on Monday. Have a great weekend. Everyone be safe Miigwetch!

06/20/2026

FRI Night update! June 19, 2026

Hello everyone, it’s been a crazy week of screwing, we finished the live room dry walling and the control room is fully ...
06/20/2026

Hello everyone, it’s been a crazy week of screwing, we finished the live room dry walling and the control room is fully insulated and ready to be dry walled. Start Mon!😁

Friday night update, what you’re seeing in the pictures is the envelope in the live room all insulated and first layer o...
05/30/2026

Friday night update, what you’re seeing in the pictures is the envelope in the live room all insulated and first layer of drywall going on and a little bit of the OSB, which is the second layer, and we built out the control room window a little bit😁

05/30/2026

FRIDAY NIGHT UPDATE!!