09/23/2026
⏳❄️ RINK SEASON: LOADING…▰▰▱▱▱▱▱▱▱▱
Things are about to start moving quickly at La Palestre!
🧹 SUNDAY, SEPT. 27 | 1–5 PM
First up: RINK CLEAN-UP!
Come for an hour or stay for the afternoon, every extra set of hands helps us get the old barn ready for another season.
❄️ SEPT. 30 — PLANT ON!
It's confirmed!!! The refrigeration plant fires up and COOLING MODE officially begins!
💧 NEXT UP: ICE INSTALLATION…
We're aiming to begin our first base floods Oct. 1 evening and Oct. 2, followed by paint, lines and logos on Oct. 3.
Then we keep walking! 👟
Once the paint is down, we’ll continue building the ice layer by layer over the next few days until there’s enough for the Zamboni to take over.
👉 WATCH FOR A POST AFTER THE WEEKEND with confirmed times and volunteer spots for anyone willing to walk the slab and help us start building those first layers of ice.
No experience necessary, just some willing feet and a little patience while we perfect the fine art of watching water freeze. 😂
Cleanup → Cool Down → Flood → Freeze → ICE.
The loading bar is about to start moving.